Timeframe
The East Perth Redevelopment Authority has a very clear vision for the redevelopment of Riverside:
Queens Precinct
Metrobus Depot site
Planning Completed
Site acquisition Completed
Subdivision work Completed
Sales October 2005 - December 2006
WA Chemistry Centre:
Planning Completed
Site acquisition End 2008
Development complete July 2009
Sales commence Aug - Oct 2009
Central Precinct
Planning completion Mid 2006
Site acquisition End 2006
Development complete 2010
Sales commence 2010
Hillside Precinct
Planning completion End 2007
Site acquisition End 2007
Development complete Mid 2009
Sales commence End 2009
Entertainment Precinct (Causeway Common)
Planning completion August 2006
Site acquisition Mid 2006
Extend Hay Street to River's edge End 2009
Development complete Mid 2011
Sales commence Jan - Dec 2011
The timeframe may be subjective to changes.